Friday, October 19, 2007

Incinerator's cost doubles

Exclusive by Jess Bauldry and Lawrence Marzouk
The construction costs of a controversial incinerator project have more than doubled from original estimates.

A total of £145.7 million will now have to be paid by waste contractor Veolia just to prepare the site in Newhaven and to build the incinerator.